Case Number
M2017-01369-COA-R3-CV
This is a contract dispute between the developer and the builder of a residential property. The developer claimed that the builder was not in compliance with the terms of the contract and removed the builder from the project. The trial court found that the developer breached the contract first by removing the builder from the property without providing it with an opportunity to cure the problems the developer identified and awarded damages to the builder. The developer appeals the decision by the trial court, and we affirm the trial court’s judgment.
Originating Judge
Chancellor Deanna B. Johnson
Case Name
The Manor Homes, LLC v . Ashby Communities, LLC, Et Al.
Date Filed
Dissent or Concur
No