Greg Calfee Builders LLC v. Neill Magee and Diane Magee

Case Number
E2019-00905-COA-R3-CV

This appeal concerns an alleged breach of contract. Greg Calfee (“Mr. Calfee”), on behalf of Greg Calfee Builders LLC (“GCB”), and Neill MaGee (“Mr. MaGee”) signed an agreement (“the Contract”) whereby GCB would custom-build a home for Mr. MaGee and his wife, Diane MaGee (“the MaGees,” collectively). Mr. MaGee, citing a number of construction defects, later terminated GCB from the job and told Mr. Calfee that GCB could not come back despite GCB’s willingness and offer to correct the defects. GCB sued the MaGees in the Chancery Court for Bradley County (“the Trial Court”) seeking to recover money it alleged was still owed to it. Mr. MaGee filed a counterclaim. GCB filed a motion for summary judgment, which the Trial Court granted. The MaGees appeal. We find and hold, inter alia, that under both Tennessee caselaw and the Contract, Mr. MaGee was required to give GCB notice and a reasonable opportunity to cure the defects, yet he failed to do so. GCB is entitled to judgment as a matter of law. We affirm.

Authoring Judge
Judge D. Michael Swiney
Originating Judge
Chancellor Jerri S. Bryant
Case Name
Greg Calfee Builders LLC v. Neill Magee and Diane Magee
Date Filed
Dissent or Concur
No
Download PDF Version