Los Pumas Concrete v. Harmony Hospitality, LLC Et Al.

Case Number
M2020-00956-COA-R3-CV

A subcontractor that performed concrete and site work on a hotel construction project filed a lien on the property and then commenced this action against the general contractor and the owner of the property to recover sums due on the balance of the subcontract, for additional change order work, and interest. The claims relevant to the issues on appeal are against the owner for unjust enrichment and to enforce the lien. After obtaining a default judgment against the now defunct general contractor, the subcontractor moved for summary judgment on its claims against the owner. The owner contended that summary judgment was not proper because there were genuine issues of material fact concerning the amount owed to the subcontractor and whether the change orders had been approved. The court found it undisputed that the subcontractor performed work, in addition to that paid by the owner to the general contractor, for which the subcontractor was not paid; and that the owner received and appreciated a benefit from the services rendered by the subcontractor. Based on these findings, the trial court held that the subcontractor satisfied its burden of proving that the property owner was unjustly enriched. Accordingly, the trial court granted summary judgment in favor of the subcontractor on its claims of unjust enrichment and to enforce its lien. We affirm the trial court in all respects.

Authoring Judge
Presiding Judge Frank G. Clement, Jr.
Originating Judge
Chancellor Ellen Hobbs Lyle
Case Name
Los Pumas Concrete v. Harmony Hospitality, LLC Et Al.
Date Filed
Dissent or Concur
No
Download PDF Version